

| TO WORK PLEASE CALL AND REGISTER SO EFFICIENT USE OF THE VOLUNTEER FORCE CAN BE PLANNED. Walk-on help may not be allowed depending upon work scheduled and numbers of volunteers signed on for that day. |
|
Call to Register to Work: |
Bill Schleichert: 608-635-2452; fatkat@centurytel.net |
| Jim Krinke: 608-592-4858; 608-575-6376 jkrinke@charter.net | |
| Bruce Koch: 608-370-2083; lbkoch@verizon.net | |
Call to Provide Meals: |
|
| This is a tentative schedule and will likely vary due to conditions that arise. Delays are expected so check with the registration numbers below to insure you are aware of the work being done on a given day. | |
| Before April 19 | Obtain map and lot corner information, finalize plans with site map, obtain building permit, get bids from various suppliers |
| April 19-24 | Excavation, footings |
| April 25 - May 1 | Cement walls completed, rough plumbing |
| May 1 | Dig and install drain tile and basin, coat / seal outer cement walls; install Styrofoam panels on outer basement walls. Build shed for storage. 1st volunteer group day. |
| May 5 | ... Continue |
| May 8 | Continue and finish above work and set sill seal and sill plate on foundation. Build floor system. Lay foam for basement floor and pour basement floor. Backfill to foundation. |
| May 9-15 | ... Above |
| May 15 | Begin framing of walls. Install electrical pedestal. |
| May 19 | Continue framing of walls and possibly install wall osb sections. |
| May 22 | Continue framing of walls – interior and exterior including bathroom support for Uniform dwelling code requirements (towel bars, handrail grab-bars bracing, etc., set showers in place. Set treated rim board for patio or rear entrance if needed. |
| May 26 | Finish framing and catch up with earlier tasks. Possibly begin placing Styrofoam on main floor walls. |
| May 29 | Holiday weekend. Set trusses and osb on roof. Fascia board. Complete gable ends and truss bracing. Roof may be vented and shingled by others. Place foam on main level sidewalls, tape seams or house wrap. |
| June 2 | ... Continue above. |
| June 5 | Electrical wiring and boxes – rough wiring done by electrical volunteers. Heating and AC duct work done by subcontractor. Continuation of plumbing. |
| June 9 | Rough landscaping, set windows and exterior doors, tape off windows, sofit and fascia installation house. |
| FIRST ENERGY STAR INSPECTION | |
| June 12 | Begin insulation of sidewalls. Finish any above work not finished. Begin outside vinyl siding on house. |
| June 16 | Finish insulation, visqueen interior, hang sheet rock on ceiling and continue exterior siding. |
| SECOND ENERGY STAR INSPECTION | |
| June 19 | Make up day of above. | June 23 | ... Continue above. |
| June 26 | Continue sheetrock installation, begin taping and mudding unless donation from subcontractors for this, continue with exterior siding. |
| June 30 | Catch up week to finish any of the above work not completed. |
| July 3 | Holiday weekend. Catch up week to finish any of above tasks |
| July 7 | Landscaping, driveway, sidewalks and front entrance ramp. |
| July 10 | Finish drywall and install attic access door. Chalking and sealing continues. |
| July 14 | Painting of walls. Prepare and trim and base needed (stain or paint). |
| July 17 | Blow in attic insulation by volunteers. |
| July 21 | Continue painting and ceiling, place vinyl or tile flooring in bathrooms and set toilets. Finish any above tasks needed. |
| July 24 | Finish painting, set bathroom cabinets, sinks, set kitchen vinyl flooring and kitchen cabinets. Final landscaping and planting of grass, trees and shrubs. Landscaping may be done earlier and / or donated by some Habitat donor. | July 28 | Finish kitchen cabinets, hang interior doors, trim doors and windows, finish closets with shelving and doors. |
| July 31 | Finish above work and clean construction debris, prepare floors for carpeting and continue any above tasks not completed. |
| FINAL ENERGY STAR INSPECTION | |
| August 1-7 | Flooring installed |
| August 7 | Make up week for schedule adjustment and final punch list completion. |
| August 2010 | Dedication date to be announced. |